Refuel Outage Work Calendar
at Exelon Nuclear Sites
Fall 2009 |
Approx Start Date |
| Peach Bottom |
13-Sep-09 |
Duration ~ 29 days |
| Byron |
14-Sept-09 |
Duration ~ 18 days |
| Braidwood |
12-Oct-09 |
Duration ~ 17 days |
| Three Mile Island |
26-Oct-09 |
Duration ~ 64 days |
| Dresden |
02-Nov-09 |
Duration ~ 25 days |
Spring 2010 |
Approx Start Date |
| Clinton |
11-Jan-10 |
Duration ~ 20 days |
| LaSalle |
08-Feb-10 |
Duration ~ 28 days |
| Quad Cities |
15-Mar-10 |
Duration ~ 28 days |
| Limerick |
22-Mar-10 |
Duration ~ 17 days |
| Byron |
19-Apr-10 |
Duration ~ 18 days |
Updated 23-July-2009