Refuel Outage Work Calendar
at Exelon Nuclear Sites

Fall 2009
Approx Start Date
Peach Bottom 13-Sep-09 Duration ~ 29 days
Byron 14-Sept-09 Duration ~ 18 days
Braidwood 12-Oct-09 Duration ~ 17 days
Three Mile Island 26-Oct-09 Duration ~ 64 days
Dresden 02-Nov-09 Duration ~ 25 days
Spring 2010
Approx Start Date
Clinton 11-Jan-10 Duration ~ 20 days
LaSalle 08-Feb-10 Duration ~ 28 days
Quad Cities 15-Mar-10 Duration ~ 28 days
Limerick 22-Mar-10 Duration ~ 17 days
Byron 19-Apr-10 Duration ~ 18 days


Updated 23-July-2009

 

 

 

Exelon is a trademark of Exelon Corporation.  All other products mentioned are registered trademarks or trademarks of their respective companies.

Copyright © 2001 Exelon.  All rights reserved.
Last modified: July 23, 2009